CENTRAL ROADS FUND (CRF)
(a) CRF works (For improvement of Road
infrastructure of H.P)
The Government of
India has sanctioned 50 No. projects (43 Roads, 7 No. Bridges) of
Rs.227.74 crore and HP.PWD. has completed 32 projects (26
Road, 6 No. bridges), 18 No. projects are in progress. The 15 Nos
works are in advance stage of completion and the tenders of 3 No. works
are under process. The HP.PWD. has incurred expenditure of Rs.90.23
crore and submitted utilization of Rs.101.28 crore and Government of
India has released Rs.90.24 crore till 31-12-2009. The
Government of
India has released Rs.12.06 crores during the year 2009-10. The
Government of India has introduced Direct Payment Procedure (DPP)
authorizing Regional Office Ministry of Road Transport & Highways
Chandigarh to release the payments directly to the Contractors w.e.f.
April, 2009 conveyed vide Ministry of Shipping Road Transport & Highways
New Delhi letter No.NH-I-11011/2009-P&M dated 27/03/2009. In suppression
of this letter, MORT&H vide this office letter No.PW-P-Cell-CRF/2009-556-62
dated 28/05/2009 has kept on hold Direct Payment Procedure (DPP) for
time being. The process of disbursement on Utilization Certificate basis
will continue for time being till the formalities are finalized.
Physical progress.
|
No. of
Projects Sanctioned |
No. of
Projects Completed |
No. of
Projects in progress |
|
Road |
Bridges
(No.) |
Road |
Bridges
(No.) |
Road |
Bridges
(No.) |
|
No. |
Length (km) |
No. |
Length
(Km) |
No. |
Length
(km) |
|
43 |
573 |
7 |
26 |
341 |
6 |
17 |
232 |
1 |
Financial Status.
|
Upto date Accrual
|
Expenditure |
Utilization sent to Government of
India. |
Funds Released by Government of
India |
|
Rs. 151.61 Crore |
Rs.101.28 Crore |
Rs.101.28 Crore |
90.24 |
12 no. proposals of CRF works of Rs.124.82 crores have been sent to
Government of India vide Principal Secretary (PW) to the Government of
H.P. letter No.PBW(B&R) 3(6)8/2003-VI dated 1st July 2009.
8 No. Detailed estimate amounting to Rs. 99.11 crores have been
sent to Government of India, out of which 4 No. estimate amounting to Rs.
73.31 crores has been approved by the Government of India.
(b) Inter State Connectivity
–Projects (ISC)
4 No. projects of Rs.17.69 Crore have been sanctioned till date under
ISC and 3 No projects with expenditure of Rs.14.60 crore have
completed. There was accrual of Rs.16.15 crore for H.P. & Government of
India has released Rs.11.80 crore till date. There is allocation of Rs.
4.35 for 2009-10.
Updated Physical
Status:
|
No. of
Projects Sanctioned |
No. of
Projects Completed |
No. of
Projects in progress |
|
Road |
Bridges
(No.) |
Road |
Bridges
(No.) |
Road |
Bridges
(No.) |
|
No. |
Length (km) |
No. |
Length
(Km) |
No. |
Length
(km) |
|
4 |
44.455 |
- |
3 |
36.57 |
- |
1 |
7.855 |
-
|
Financial
Status
|
Upto Accrual
|
Upto Expenditure |
Utilization sent to Government of
India. |
Funds Released by Government of
India |
|
Rs. 16.15 Crore |
Rs.14.60 Crore |
Rs.14.60 Crore |
Rs.11.80 Crore.
|
(c). Economic Importance Projects
(E.I).
No. projects of Economic
Importance has been proposed by Government of H.P. There is allocation
of Rs.4.02 crore for 2009-10. The Government of India has given
in-principle approval of 1 No. project of Rs.8.94 crore and has asked to
prepare the detailed estimate to seek final sanction. However, the H.P.
Government has requested Government of India for changing this sanctions
under strategic Roads Head as the road belongs to Border Roads
Organization and its 100% Improvement/Maintenance is to be done with the
Government of India funds only, as decided at the time of transfer of
this road to the State in year 2007.
The DPR of Rs.95.83 crores of Improvement of
Basantpur to Dhami road has been sent to Government of India vide
Principal Secretary (PW) to H.P.Govt. letter No.PBW(B)F(5)65/2009 dated
02/02/2010. This road is being widening for the in/ out bound traffic of
cement plant of M/S Lafarge India Ltd. who have agreed to bear the 50%
share of this
work.The DPR has been received from MORTH with some
observations.
|